FAR 52.234-3

FAR 52.234-3 Notice of EVMS Post-Award IBR Clause – dated November 2016

This clause has the same requirements as FAR 52.234-2 except that it is post-award.  A contractor must submit either documentation that its earned value management system (EVMS) has been determined to be compliant with the EIA-748 or a plan to achieve compliance.  The clause also requires that the contractor and the Government agree to subcontractors selected for application of the EVMS guidelines.

Download Document

Shopping Cart