Budget Baseline Support
Posted: 09/02/2011
Budget Baseline Support as Part of EVMS Implementation
H&A uses the integrated master schedule (IMS) as a basis to assist control account managers (CAMs) in establishing the performance measurement baseline (PMB). We can assist you in developing the ...
-
Data Quality Checks
Posted: 09/02/2011
Importance of Data Quality Checks
An important part of the EVMS implementation process, especially during the first few months, is the continual monitoring of the system's data integrity. H&A can review the data produced to ensure the system ...
-
Performance and Analysis Cycle
Posted: 09/02/2011
Performance and Analysis Cycle as Part of EVMS Implementation
Once the project baseline is established, it is important to establish a consistent and disciplined weekly or monthly performance measurement and analysis business rhythm. Typically the activities outlined below ...
-
Responsibility Assignment Matrix (RAM)
Posted: 09/02/2011
Importance of the Responsibility Assignment Matrix (RAM)
Determining the level of a project's control accounts can be challenging. Too low, and the maintenance of the system can outweigh the benefits. Too high, and the information received is of ...
-
Scheduling Support
Posted: 01/20/2012
Scheduling Support and EVMS Implementation
A quality integrated master schedule (IMS) is critical to the success of a project. The IMS identifies the work effort (activities), significant events (milestones), time allocation (activity durations), sequence of work (activity relationships), ...
-
Self Surveillance Plans
Posted: 04/16/2015
EVMS Implementation through Self Surveillance Plans
The purpose of a self surveillance plan is to establish the process and methods used to conduct internal system reviews. Conducting self surveillance is a useful best practice to verify your EVMS ...
-
Training Plan
Posted: 09/02/2011
Training Plans and EVMS Implementation
For an EVMS implementation to succeed, the end users have to fully embrace the new or enhanced project control system. It is important they understand the underlying principles of EVMS, why they are ...
-
Work Breakdown Structure (WBS)
Posted: 09/02/2011
Work Breakdown Structure (WBS) and EVMS Implementation
Implementing a single work breakdown structure (WBS) that reflects the technical scope of work is critical for organizing and managing the work for the life of the project. H&A can assist ...
-
-
-
-
-
-
-